In every project it is important to define defined milestones.
These milestones can be created in smenso Cloud by creating a task.
The data to be filled is identical to the creation of a task. However, there is one exception.
Only the start date or the due date is entered.
We recommend entering it in the end date field. The date is then also displayed in the task tile in the task overview.
The entry in the start date field also creates a milestone, but the date is not displayed in the task overview in the task tile.
This milestone is displayed in the Timeline as a hash and marked with a green vertical line.