Dependencies define the chronological relationship between tasks, milestones, and phases. This allows you to represent which planning elements must begin or be completed first and which ones follow afterwards.
In the Gantt chart, these relationships are represented by connection lines between the bars. Dependencies can be created directly in the chart and then used for further scheduling.
Dependency types in Gantt
Four standard dependency types are available in Gantt. The type that is created depends on which start or end points of the two bars are connected.
-
Finish-to-Start
The successor task can only begin once the predecessor task has been completed. -
Start-to-Start
The start of the successor task is based on the start of the predecessor task. -
Finish-to-Finish
The end of the successor task is based on the end of the predecessor task. -
Start-to-Finish
The successor task can only end once the predecessor task has started.
Note
The Finish-to-Start dependency is used particularly often because it represents the standard sequence “complete task A, then begin task B.”
Create a dependency graphically
Dependencies can be created directly between the task bars in Gantt.
- Move the mouse pointer over the bar of the task from which the connection should originate.
- The available connection points appear at the beginning and end of the bar.
- Hold down the
left mouse buttonat the desired connection point. - Drag the connection to the beginning or end of the desired target task.
- Release the mouse button at the corresponding connection point.
The tasks are connected. The corresponding dependency type is determined automatically based on the selected start and end points.
Display dependencies on hover
Move the mouse pointer over a task to highlight its dependencies directly. The associated connection lines become visible, and an information window provides a compact overview of which tasks are linked to the selected entry.
You can distinguish between the task’s predecessors and successors:
- The entry pointing to the left shows a task that the selected task depends on.
- The entry pointing to the right shows a task that depends on the selected task.
This allows you to trace a task’s dependencies without having to open the task details.
Manage dependencies using fields
As an alternative to graphical linking, you can also manage dependencies using the task fields Blocked by and Blocks.
-
Blocked bycontains the predecessors that must be taken into account first. -
Blockscontains the successor tasks that depend on the current task.
Show the required fields in the task list of the Gantt chart and select the desired task or milestone in the respective cell.
Define lag and lead
A dependency can also include a time offset. This means that the successor task does not necessarily have to begin or end immediately at the linked date.
-
Positive lag
Adds a delay between the linked tasks. One example is a required waiting or drying period. -
Negative lag or lead
Allows the successor task to begin before the predecessor has been fully completed.
Link phases and milestones
Dependencies can be created not only between regular tasks. Milestones and summary phase bars can also be linked to other planning elements.
This allows you, for example, to define that a new project phase may only begin after a previous phase has been completed or a milestone has been reached.
Show and hide dependencies
In extensive project plans, a large number of connection lines can make the view difficult to read. You can therefore show or hide dependencies using the corresponding button in the toolbar.
Even when connection lines are hidden, you can still see the dependencies of an individual task by moving the mouse pointer over the corresponding bar.
Remove a dependency
You can remove a dependency that is no longer required using the corresponding dependency fields.
- Show the appropriate
Blocked byorBlocksfield in the task list. - Open the cell of the corresponding task.
- Remove the link that is no longer required.
The connection line is then also removed from the Gantt chart.
Interaction between start, due date, and duration
The fields Start, Due date, and Duration are interdependent. As soon as two of these fields are filled in, the third field is calculated automatically.
When entering the values for the first time, the order in which you enter them determines which third field is calculated.
If all three fields are already filled in and one value is then changed, Duration is treated as the prioritized value:
- Start is changed: The duration remains unchanged and the due date is recalculated.
- Due date is changed: The duration remains unchanged and the start is recalculated.
- Duration is changed: The start remains unchanged and the due date is recalculated.
If you want to change the due date independently of the previous duration, you can first remove the value from the Duration field and then define a new due date.
Note
Direct editing in the Gantt chart is an exception. There, you can change the beginning or end of a task bar using drag & drop. The duration is adjusted to the newly defined time period.
Effects on automatic scheduling
Together with duration and possible date constraints, dependencies form the basis for automatic scheduling.
During forward or backward scheduling, smenso takes the stored relationships into account and calculates suitable start and due dates for the affected tasks.
Suggested date changes are first displayed in a preview. They are only applied to the project plan after you confirm them.
Note
If you change dependencies, lags, durations, or date constraints, the result of the next automatic scheduling process may change accordingly.
Further information
You can find more information about working with tasks and managing dependencies in the following articles: