A project template can be used in two ways: You can create a brand new project directly from a template, or You can update an already existing project with a template's master data. To learn how to define a project template, see the article Managing Project Templates.
Important difference
When creating a new project from a template, tasks from the template can also be carried over. When a template is applied to an existing project, however, only master data (default fields as well as flavors and flavor groups) is applied - tasks and other structures from the project template are not carried over in this case.
Creating a new project from a project template
When creating a project, You can choose whether to start from scratch ("Empty project") or to start with an existing project template.
Create a project from a project template as follows:
- Select the
+ New projectbutton in the main navigation on the left. - Select
Use template/Choose from templates. - Select a project template from the list of templates.
- In a few steps, the wizard guides You through project creation based on Your selected project template. These fields are required:
- Project name
- Project type
- Project folder
- In the next step, choose whether to take over the start date from the template or select new dates for the project. With
Choose new dates, You can set either a new start date or a new end date. The respective other date is automatically calculated based on the tasks contained in the template. The start and due dates of the tasks are adjusted accordingly. - Select which properties from the project template should be carried over into the new project. You can either take over everything 1:1, or make a custom selection.
- Select the project's visibility (Open or Private).
- In the last step, You can also choose whether to initially create the project as inactive, whether to set Yourself as a watcher right away, and whether You want to jump into the project (i.e. the new project opens directly).
Note
Project templates are only shown once projects have previously been defined as project templates in the workspace.
Applying a project template to an existing project
In project management, existing projects can be updated with a project template. Certain data fields can be applied without overwriting existing content. This allows for a quick and efficient adjustment of projects based on a template.
What is applied from the template?
Only the master data of the project template is applied to the existing project. This includes:
- Default fields
- Flavors & flavor groups
Tasks and other structures from the project template are not applied.
Opening project settings
To apply a project template to an existing project, You first need to open the project settings.
- Open the desired project.
- Click the three-dot menu (
...) in the top right. - Select
Manage project.
Opening the template menu
In the Master data section, You'll find the Manage templates button in the top right, which lets You select an existing project template.
Selecting and applying a project template
- Select
Import everythingorCustom. - If
Customwas selected, mark the desired data fields. - Optionally enable the
Overwrite valuessetting if existing values should be replaced. - Click
Applyto apply the template.
Overwrite values
If the Overwrite values option is enabled, existing values in the project are replaced by the values contained in the template. If disabled, existing values are preserved.
Notes
- This function is only available to users with the
Adminrole, as it can change existing projects on a large scale. - The
Customoption lets You specifically control which elements are applied from the template. - Tasks and other structures from the project template are not applied.
Example
Suppose You have a project with 5 flavors, but You've since added 5 more flavors to the project template. After applying the template, Your project will consequently have 10 flavors, and this adjustment is applied including the flavor groups and assignments, exactly as they are defined in the template.
Note
This function is designed to be applied to only a single project at a time in the user interface. If You want to apply this function to multiple projects at once, You can do so via the smenso integration API. More information can be found in the article API endpoint: Template.
Comments
0 comments
Please sign in to leave a comment.